    If it’s fixed price and prices go up, the options are

    1. construction company makes a loss. They will do all they can to avoid this, so

    2. they use inferior quality (cheaper) materials and/or cut corners

    3. or they themselves negotiate fixed prices or discounts with suppliers…for suppliers then see 1 and 2

    1 Reply Last reply
    1
  • HoorooH Offline
    HoorooH Offline
    Hooroo
    wrote on last edited by
    #771

    Decision day happening at the moment.

    I hope @shark is there supporting the cause (or what’s left of it)

    It will be a disgrace if they don’t go ahead

    KiwiwombleK 1 Reply Last reply
    0
  • KiwiwombleK Online
    KiwiwombleK Online
    Kiwiwomble
    replied to Hooroo on last edited by
    #772

    @Hooroo isn't it decided? i thought they'd agreed the new contract

    HoorooH 1 Reply Last reply
    1
  • HoorooH Offline
    HoorooH Offline
    Hooroo
    replied to Kiwiwomble on last edited by Hooroo
    #773

    @Kiwiwomble said in Stadium of Canterbury:

    @Hooroo isn't it decided? i thought they'd agreed the new contract

    Nah. They are deciding today. It’s live on stuff.

    Non binery folk aren’t supportive, it appears. (This was in the submission a few moments ago)

    gt12G 1 Reply Last reply
    0
  • gt12G Offline
    gt12G Offline
    gt12
    replied to Hooroo on last edited by gt12
    #774

    @Hooroo said in Stadium of Canterbury:

    @Kiwiwomble said in Stadium of Canterbury:

    @Hooroo isn't it decided? i thought they'd agreed the new contract

    Nah. They are deciding today. It’s live on stuff.

    Non binery folk aren’t supportive, it appears. (This was in the submission a few moments ago)

    Interesting, you'd think that they wouldn't assume it as a yes / no distinction.

    1 Reply Last reply
    2
  • HoorooH Offline
    HoorooH Offline
    Hooroo
    wrote on last edited by
    #775

    Council voted 13:3 in favour of spending the “fixed” $683m

    Yay. Build the damn thing

    1 Reply Last reply
    3
  • StargazerS Offline
    StargazerS Offline
    Stargazer
    wrote on last edited by
    #776

    1 Reply Last reply
    0
  • nzzpN Online
    nzzpN Online
    nzzp
    wrote on last edited by
    #777

    That is a tremendous entertainment and terrible financial decision.

    KiwiwombleK 1 Reply Last reply
    0
  • KiwiwombleK Online
    KiwiwombleK Online
    Kiwiwomble
    replied to nzzp on last edited by
    #778

    @nzzp yeah...i imagine this thread will keep running with lots of things to talk about during construction

    1 Reply Last reply
    0
  • StargazerS Offline
    StargazerS Offline
    Stargazer
    wrote on last edited by
    #779

    1 Reply Last reply
    1
  • M Offline
    M Offline
    Mackerzzzz
    replied to taniwharugby on last edited by
    #780

    @taniwharugby said in Stadium of Canterbury:

    who would take on a fixed price contract in the current climate, unless your price is way above market?

    Sure you price in contingencies, but the world be crazy and prices escalating, and the time frames involved here...

    https://www.stuff.co.nz/national/129249542/fixedprice-contract-negotiated-for-christchurch-stadium

    From a business perspective that's the most stupid decision I have ever seen. If another price hike hits you have basically garenteed that your business is going down the drain. And at best the building company has garenteed that they won't make money on the job.

    KiwiwombleK 1 Reply Last reply
    0
  • KiwiwombleK Online
    KiwiwombleK Online
    Kiwiwomble
    replied to Mackerzzzz on last edited by
    #781

    @Mackerzzzz thats not true, they have not guaranteed they wont make any money, they made the deal at the tail of covid when shipping materials was the hardest, lots to suggest they will become easier to source....and they will have hiked a huge premium onto the price to be locked in....the construction company is the last one im worried about

    1 Reply Last reply
    1
  • KiwiwombleK Online
    KiwiwombleK Online
    Kiwiwomble
    wrote on last edited by
    #782
    Jan 12, 2023  /  City life

    Major concrete pours for Te Kaha to begin later this month

    Major concrete pours for Te Kaha to begin later this month

    Work on Te Kaha, Canterbury’s Multi-Use Arena, will hit a new milestone later this month when the first of the foundations’ major concrete pours is completed.

    New Christchurch Stadium | One NZ Stadium

    New Christchurch Stadium | One NZ Stadium

    One NZ Stadium is the new Christchurch stadium in the centre of Otautahi, Christchurch, the ideal place to host all the biggest and best games, gigs and…

    thought there might be some webcams or something but couldn't see any, regularly checked in on the webcams for Forsyth Barr

    antipodeanA dogmeatD 2 Replies Last reply
    1
  • antipodeanA Offline
    antipodeanA Offline
    antipodean
    replied to Kiwiwomble on last edited by
    #783

    @Kiwiwomble I'm astonished they're actually commencing work on this.

    KiwiwombleK 1 Reply Last reply
    1
  • KiwiwombleK Online
    KiwiwombleK Online
    Kiwiwomble
    replied to antipodean on last edited by
    #784

    @antipodean said in Stadium of Canterbury:

    @Kiwiwomble I'm astonished they're actually commencing work on this.

    doesn't seem like a cracking pace considering it was signed off in July last year

    1 Reply Last reply
    0
  • dogmeatD Offline
    dogmeatD Offline
    dogmeat
    replied to Kiwiwomble on last edited by
    #785

    @Kiwiwomble

    Artist's impression, subject to design development
    
    KiwiwombleK 1 Reply Last reply
    0
  • KiwiwombleK Online
    KiwiwombleK Online
    Kiwiwomble
    replied to dogmeat on last edited by
    #786

    @dogmeat ?

    dogmeatD 1 Reply Last reply
    0
  • dogmeatD Offline
    dogmeatD Offline
    dogmeat
    replied to Kiwiwomble on last edited by
    #787

    @Kiwiwomble All the renders of the stadium have that caveat attached.

    Pretty pictures mean SFA once the value engineers get their mitts on a design.

    KiwiwombleK 1 Reply Last reply
    0
  • KiwiwombleK Online
    KiwiwombleK Online
    Kiwiwomble
    replied to dogmeat on last edited by Kiwiwomble
    #788

    @dogmeat ok, just confirming the context, you referring to my comment on the progress? as in they may have gone back to the drawing board? ture in principle but to reliably submit a tender price (especially a fixed price) they will have had to be more than 80-90% reference design (if not well into detail design), meaning the things outstanding will be the door handles and paint colour

    1 Reply Last reply
    0
  • StargazerS Offline
    StargazerS Offline
    Stargazer
    wrote on last edited by
    #789

    Didn't they have problems getting rid of one particular building on the site, because the owners refused to sell? Or was that longer ago? This has been going on for so long, that I've trouble with the time line.

    KiwiwombleK 1 Reply Last reply
    1

Stadium of Canterbury
Sports Talk
canterburycrusaders
  • Login

  • Don't have an account? Register

  • Login or register to search.
  • First post
    Last post
0
  • Categories
  • Login

  • Don't have an account? Register

  • Login or register to search.